Plan Background
1971 | | Dana Point Harbor opens | 1997 | | The Dana Point Harbor Concept Plan is continually refined, based on input from merchants, boat owners, homeowners and other key community leaders
Refined plan is introduced to general public for continued refinement | 2003 | | The refined concept plan, which reflects the Task Force's original Plan Priorities as well as the input of today's community leaders and residents, will be presented to the Orange County Board of Supervisors for approval
County will develop a Dana Point Harbor Master Plan
The plan will undergo final design
Project Dimensions, Inc. has been selected by the Board of Supervisors to oversee the revitalization master plan as the contract administrator and project manager RBF Consulting begins developing the Environmental Impact Report for the project
A.C. Martin, Inc. has been selected as the Architectural / Engineering firm to complete the design, permitting and construction of the Dana Point Harbor concept master plan for revitalization | 2005 | | Draft Environmental Impact Report ready for public review
Orange County Planning Commission recommends certification of the Environmental Impact Report | 2006 | | Orange County Board of Supervisors certifies the Environmental Impact Report and approves the Revitalization Plan
City of Dana Point approves the Dana Point Harbor Revitalization Plan and District Regulations
Submitted Local Coastal Program Amendment to the California Coastal Commission
Launch ramp renovation begins | 2007 | | Work with the California Coastal Commission on processing the Local Costal Program Amendment (LCPA)
Begin Draft of Subsequent Environmental Impact Report (SEIR) for Waterside portion of the Revitalization Project
Launch Ramp renovation completed on time and on budget | 2008 | | Harbor dredging begins | | | | | Worked with the California Coastal Commission on public hearing schedule for Local Costal Program Amendment (LCPA) - Land Use Planning (LUP) Phase | | 2009 | | California Coastal Commission Approval of Local Costal Program Amendment (LCPA) - Land Use Planning (LUP) Phase | | 2010 | | City of Dana Point Harbor public hearing and unanimous approval of Local Costal Program Amendment (LCPA) - Land Use Planning (LUP) Phase Final certification of Local Costal Program Amendment (LCPA) - Land Use Planning (LUP) Phase by California Coastal Commission | | 2011 | | Public hearing for Local Costal Program Amendment (LCPA) - Implementation Plan (IP) Finalize Draft Subsequent Environmental Impact Report (SEIR) for Phase II. for public review | | 2012 | | Finalize Coastal Development Planning process for Phase I. Finalize Subsequent Environmental Impact Report (SEIR) for Phase II. | | 2013 | | Phase I. construction begins Coastal Development Planning process for Phase I. | | 2014 | | Phase II. Construction begins | | |
|
 |
|
|