Plan Background

1971
 


Dana Point Harbor opens
1997
 


The Dana Point Harbor Concept Plan is continually refined, based on input from merchants, boat owners, homeowners and other key community leaders

Refined plan is introduced to general public for continued refinement
2003
 


The refined concept plan, which reflects the Task Force's original Plan Priorities as well as the input of today's community leaders and residents, will be presented to the Orange County Board of Supervisors for approval

County will develop a Dana Point Harbor Master Plan

The plan will undergo final design

Project Dimensions, Inc. has been selected by the Board of Supervisors to oversee the revitalization master plan as the contract administrator and project manager

RBF Consulting begins developing the Environmental Impact Report for the project

A.C. Martin, Inc. has been selected as the Architectural / Engineering firm to complete the design, permitting and construction of the Dana Point Harbor concept master plan for revitalization

2005

 

 


Draft Environmental Impact Report ready for public review

Orange County Planning Commission recommends certification of the Environmental Impact Report
2006

 

 

 


Orange County Board of Supervisors certifies the Environmental Impact Report and approves the Revitalization Plan

City of Dana Point approves the Dana Point Harbor Revitalization Plan and District Regulations

Submitted Local Coastal Program Amendment to the California Coastal Commission

Launch ramp renovation begins
2007
 


Work with the California Coastal Commission on processing the Local Costal Program Amendment (LCPA)

Begin Draft of Subsequent Environmental Impact Report (SEIR) for Waterside portion of the Revitalization Project

Launch Ramp renovation completed on time and on budget
2008


Harbor dredging begins
 
   

Worked with the California Coastal Commission on public hearing schedule for Local Costal Program Amendment (LCPA) - Land Use Planning (LUP) Phase

 
2009
 


California Coastal Commission Approval of Local Costal Program Amendment (LCPA) - Land Use Planning (LUP) Phase
 
2010
 


City of Dana Point Harbor public hearing and unanimous approval of Local Costal Program Amendment (LCPA) - Land Use Planning (LUP) Phase

Final certification of Local Costal Program Amendment (LCPA) - Land Use Planning (LUP) Phase by California Coastal Commission

 
2011


Public hearing for Local Costal Program Amendment (LCPA) - Implementation Plan (IP)

Finalize Draft Subsequent Environmental Impact Report (SEIR) for Phase II. for public review

 
2012


Finalize Coastal Development Planning process for Phase I.

Finalize Subsequent Environmental Impact Report (SEIR) for Phase II.

 
2013
 
Phase I. construction begins Coastal Development Planning process for Phase I.

 

 

2014

 


Phase II. Construction begins

 

 